RW silicium GmbH
Delivery and installation of parts for the expansion of a filter unit in Pocking, Germany.
SGS was contracted for the complete delivery (except technical equipment), installation and cladding of parts for the upgrade of the filter system. To be precise, SGS was responsible for the installation of piping, sheet metal components, screws and steel construction as well as bottom caps and filter hosing etc. After the installation of the filter system and piping, the four ovens were integrated into the system with only four days of down time. ...
more...

HeidelbergCement
The mechanical and electrical installation of a double filter system designed for rotary kiln dedusting at HeidelbergCement in Heidelberg Germany.
The project at the company included the mechanical and electrical installation of two new filter plants for the rotary furnace dedusting. Since the existing plants for the flue gas cleaning didn‘t correspond any longer to the current pure gas content specifications (emission specification), the company HeidelbergCement had to invest in new filter plants. ...
more...
 |  |  |  |  |  |  |  |
 |
| Scheuch GmbH |  | Böhler Kapfenberg (Austria) |  | Mechanical Installation of a bag-filter plant including the piping for the hall-dedusting of the casting- and melding house. |  | April – October 2009 |
 |  |  |  |  |  |  |  |
 |
| Aktor |  | Dubai (UAE) |  | Electrical installation of a Sewage Treadment Plant Jebel Ali |  | |
 |  |  |  |  |  |  |  |
 |
| RW silicium |  | Pocking (Germany) |  | Supply and mechanical and electrical installation of sections to extend the filter system for silicium-kiln. |  | September 2007 – January 2008 |
 |  |  |  |  |  |  |  |
 |
| Siemens VAI |  | Metallurgical plant Dillingen (Germany) |  | Mechanical Installation including manufacturing of the steel construction and piping for the secondary dust removal system. |  | May – October 2009 |
 |  |  |  |  |  |  |  |
 |
| AE & E |  | Karlsruhe (Germany) |  | Mechanical installation of a complete flue gas gleaning system including additional installation of the Stack Equipment and the pipelines. |  | February 2009 – end of 2010 |
 |  |  |  |  |  |  |  |
 |
| Scheuch GmbH |  | |  | Mechanical installation of the dedusting of a granulated blast furnace slag grinding plant at Cimalux in Luxemburg. |  | August - December 2008 |
 |  |  |  |  |  |  |  |
 |
| Siemens VAI Metals Technologies GmbH & CoKG |  | Eisenhüttenstadt (Germany) |  | Installation of the electric filter case . Mechanical demounting and installation of the primer dedusting system in Eisenhüttenstadt. |  | August 2008 - March 2009 |
 |  |  |  |  |  |  |  |
 |
| Voest Alpine Meros |  | Linz (Austria) |  | Mechanical installation of a sinter-bond de dusting plant (particulate matter). Delivery of approx. 1200 tons components (steel construction, piping and insulating). |  | 2006 - 2008 |
 |  |  |  |  |  |  |  |
 |
| RW Silicium |  | Pocking (Germany) |  | Supply and installation of pipelines, roofing, running- and appendage boards, sheet-Metal parts, screws, steel constructions and components for the extension of the filter system. |  | September 2007 - January 2008 |
 |  |  |  |  |  |  |  |
 |
| Heidelberger Zement |  | Schelklingen (Germany) |  | Demounting of two electric-filters. Installation of two chamber filters for the dedusting of the rotary kiln and vantilators as a replacement for the electric-filters. |  | October 2007 - May 2008 |
 |  |  |  |  |  |  |  |
 |
| Heidelberge Zement |  | Leimen (Germany) |  | Demounting of an electric-filter. Installation of a chamber-filter for the dedusting of the rotary kiln and ventilators as a replacement for the electric-filter. |  | October 2007 - February 2008 |
 |  |  |  |  |  |  |  |
 |
| Stahlwerke Lingen |  | Lingen (Germany) |  | Mechanical installation of a filter plant including evaporation cooler. |  | February - August 2007 |
 |  |  |  |  |  |  |  |
 |
| Scheuch GmbH |  | |  | Installation of a chip exhaustion, Ligno filter systems incl. piping, HD dust transport and silo filter at the company “Oeri Schallung und Gerüstung”. |  | March - August 2007 |
 |  |  |  |  |  |  |  |
 |
| Binder Holz |  | Kösching (Germany) |  | Installation of an electric filter plant, including multiklon and heat exchanger. |  | February - June 2007 |
 |  |  |  |  |  |  |  |
 |
| Siemens VAI |  | Linz (Austria) |  | Installation and delivery of a complete sinter flue gas dedusting plant for Siemens VAI. |  | October 2006 - July 2007 |
 |  |  |  |  |  |  |  |
 |
| Wotan Portland Zementwerk |  | Üxheim (Germany) |  | Mechanical assembly of a kiln dedusting. |  | |
|
|
We also install environmental protection technology for our customers in the metal, stone-earth-cement, wood and wood based panels and energy generation sectors. Our service range in this area includes the mechanical and electrical installation of bag filters, electrostatic filters, condensation and absorption systems, extraction ductwork systems, DeNOx units, flue gas cleaning units, pneumatic conveying systems, ventilators, sifting plants and evaporation coolers. Thanks to our proven know-how, we can also procure low-tech components, such as steel structures, pipelines and insulation systems, for you anywhere in the world.
|
We are looking for executives and specialist employees for projects abroad
|