PG Bison
Installation of a Siempelkamp chipboard plant in Ugie, South Africa
This was the first project for SGS on the African continent. The city of Ugie is approx. 800 kilometers south of Johannesburg in a previous Homeland. Because of the very poor infrastructure in this region, a large challenge was to find housing, transport, meals etc. which come close to European standards for the SGS mechanics. ...
more...

Satipel, Brazil
Mechanical and electrical installation of a Siempelkamp MDF plant at Satipel;
Mechanical and electrical installation of a Siempelkamp forming and pressing line, cooling and unloading station, sanding and packaging line, gluing and suction units.
Uberaba: Our first large project in Brazil was completed in June 2008. The project involved the mechanical and electrical installation of a Siempelkamp chipboard froming and pressing line, cooling and unloading station, the sanding line and the packing unit. At peak times there were 70 mechanics on location in Uberaba, Minas Gerais. ...
more...
MLT (Modern Lumber Technologies)
Mechanical and electrical installation of a LVL production line in Torzhok, Russia.
The LVL production line-project started in May 2008 for the customer Modern Lumber Technology (MLT) in Torzhok Russia. With the LVL technology, plywood is produced which is mainly used in the construction and packaging industry. ...
more...
Gagarin Plywood Mill
Installation of a Dieffenbacher chipboard plant in Gagarin, Russia.
Syktyvkar Plywood planned the construction of a new plant in Gagarin located west of Moscow. SGS was contracted for the mechanical and the electrical installation of parts of a Dieffenbacher chipboard production line. The project consisted of the installation of a forming and pressing line, finishing, pneumatic transport system and energy production of approximately 200 tons of steel construction. SGS completed the project from January – June of 2008. On 1 September 2008, the first board was produced. ...
more...
 |  |  |  |  |  |  |  |
 |
| EMOS Ltd. |  | Kaisersesch (Germany) |  | Mechanical and electrical dismantling of a short cycle laminating plant in Kaisersesch including the transport of the plant components to Chirpan (Bulgaria). |  | April – September 2009 |
 |  |  |  |  |  |  |  |
 |
| Modern Lumber Technologies (MLT) |  | Torzhok (Russia) |  | Mechanical and electrical installation of a complete LVL-line, a drying line and a Vitech roundwood feeder. |  | March 2008 - May 2009 |
 |  |  |  |  |  |  |  |
 |
| Dieffenbacher GmbH & Co KG |  | Dingolfing (Germany) |  | Mechanical and electrical installation of a deep drawing press at BMW-Dingolfing. |  | July - September 2009 |
 |  |  |  |  |  |  |  |
 |
| Gagarin Plywood Mill |  | Gagarin (Russia) |  | Mechanical and electrical installation of a Dieffenbacher particle board plant as well as 3 Wemhöner short cycle laminating lines. |  | January - June 2008 |
 |  |  |  |  |  |  |  |
 |
| Satipel |  | Uberaba and Taquari (Brazil) |  | Mechanical and electrical installation of a Siempelkamp MDF plant at Satipel.
Mechanical and electrical installation of a Siempelkamp forming and presings line, cooling and unloading station, sanding and packaging line, gluing and suction units. |  | November 2007 – June 2008 |
 |  |  |  |  |  |  |  |
 |
| Egger Radauti |  | Romania |  | Mechanical and electrical installation of two Wemhöner short cycle laminating plants. |  | July 2007 - February 2008 |
 |  |  |  |  |  |  |  |
 |
| Modern Lumber Technologie (MLT) |  | Torzhok (Russia) |  | Mechanical and electrical installation of a complete LVL-line, a Grenzebach drying line and a Vitech Roundwood task. |  | March - September 2008 |
 |  |  |  |  |  |  |  |
 |
| Sonae White River |  | South Africa |  | Mechanical and electrical installation of a Wemhöner short cycle laminating line. |  | May - July 2008 |
 |  |  |  |  |  |  |  |
 |
| SHS-Hörmann |  | Ichtershausen (Germany) |  | Mechanical and electrical installation of a double belt sandwich panel line. |  | May - June 2008 |
 |  |  |  |  |  |  |  |
 |
| SHS-Romakowsky |  | Buttenwiesen (Germany) |  | Mechanical and electrical installation of two double belt sandwich panel lines. |  | since August 2008 |
 |  |  |  |  |  |  |  |
 |
| SHS-Egger ROL |  | Rion (France) |  | Mechanical and electrical installation of a Vits impregnation line and the finishing line. |  | August - November 2008 |
 |  |  |  |  |  |  |  |
 |
| Glunz AG |  | Horn/Bad Meinberg (Germany) |  | Mechanical rebuilding works of the spreading and chipping. |  | June - August 2008 |
 |  |  |  |  |  |  |  |
 |
| Glunz AG |  | Meppen (Germany) |  | Rebuilding works at the board separation and finishing line. |  | June 2008 |
 |  |  |  |  |  |  |  |
 |
| Kronospan LPW |  | Germany |  | Mechanical and electrical installation of a Wemhöner short cycle laminating plant. |  | March - June 2007 |
 |  |  |  |  |  |  |  |
 |
| Siempelkamp |  | Egger (Romania) |  | Mechanical and electrical installation of a forming- and pressing line including the gluing for the chipboard pressing line. |  | June - November 2007 |
 |  |  |  |  |  |  |  |
 |
| PG Bison |  | Ugie (South Africa) |  | Mechanical and electrical installation of a Siempelkamp forming and pressing line including gluing, finishing line, steel construction and an Anthon Saw. |  | June - November 2007 |
 |  |  |  |  |  |  |  |
 |
| Kronotec |  | Alabama (USA) |  | Mechanical installation of a Dieffenbacher MDF forming- and pressing line includingthe Kontra finishing line. |  | June - November 2007 |
 |  |  |  |  |  |  |  |
 |
| Unopan Tableros de Fibras |  | Sallas (Spain) |  | Mechanical and electrical installation of a Dieffenbacher MDF plant including delivery and installation of 1.600 to steel construction as well as 240.000 m cable. |  | March 2007 - March 2008 |
 |  |  |  |  |  |  |  |
 |
| Meister Werke |  | Germany |  | Mechanical and electrical installation of a Wemhöner short cycle laminating plant. |  | September - November 2007 |
 |  |  |  |  |  |  |  |
 |
| Kronospan |  | Zvolen (Slowakia) |  | Mechanical and electrical installation of a Siempelkamp short cycle laminating plant. |  | September - December 2007 |
 |  |  |  |  |  |  |  |
 |
| Kronospan |  | Mofa (Hungary) |  | Mechanical and electrical installation of a Dieffenbacher MDF-plant. |  | November 2006 - March 2007 |
 |  |  |  |  |  |  |  |
 |
| Kronospan Bolderaja |  | Riga (Latvia) |  | Mechanical and electrical installation of an OSB-board production line, from gluing to stacking, including key and slot plant and packaging line. |  | November 2006 - June 2007 |
 |  |  |  |  |  |  |  |
 |
| Kronospan |  | Bischweier (Germany) |  | Demounting and electrical installation of two Dieffenbacher short cycle laminating lines. |  | November 2006 - April 2007 |
 |  |  |  |  |  |  |  |
 |
| Fiberboard GmbH |  | Baruth (Germany) |  | Mechanical and electrical installation of an MDF-production line including the cooling- and stacking line, storing and finishing line. |  | December 2006 - May 2007 |
 |  |  |  |  |  |  |  |
 |
| Kronospan LPW |  | Germany |  | Mechanical and electrical installation of a Wemhöner short cycle laminating plant. |  | February - May 2006 |
 |  |  |  |  |  |  |  |
 |
| Kronowood |  | Egorievsk (Russia) |  | Mechanical and electrical installation of a Dieffenbacher forming and pressing line. |  | January - June 2006 |
 |  |  |  |  |  |  |  |
 |
| Siempelkamp GmbH |  | Krefeld (Germany) |  | Mechanical and electrical installation of a Siempelkamp Contitherm pressing line including function tests at the company Gutex in Waldshut-Tiegen. |  | August 2005 - February 2006 |
 |  |  |  |  |  |  |  |
 |
| Hornitex |  | Beeskow (Germany) |  | Mechanical and electrical installation of a Wemhöner short cycle laminating plant. |  | November 2005 - January 2006 |
 |  |  |  |  |  |  |  |
 |
| Kronospan |  | Jihlava (Czech Republic) |  | Mechanical installation of a Dieffenbacher forming and pressing line in Jihlava. |  | January - April 2005 |
 |  |  |  |  |  |  |  |
 |
| Vits Systems GmbH |  | Langenfeld (Germany) |  | Supervision for the installation of a paper impregnation channel at the company „Egger Holzwerkstoffe“ in Wismar. |  | July - August 2005 |
 |  |  |  |  |  |  |  |
 |
| H. Wemhöner GmbH & CoKG |  | Germany |  | Mechanical and electrical installation of a short cycle laminating plant at „Berry Floor“/Belgium. |  | May - June 2005 |
 |  |  |  |  |  |  |  |
 |
| Interbon S.A. |  | Burgos (Spain) |  | Mechanical and electrical installation of an MDF-plant as well as delivery and installation of the steel-construction components. |  | October 2004 - May 2005 |
 |  |  |  |  |  |  |  |
 |
| Egger |  | Rambervillers (France) |  | Mechanical and electrical installation of a short cycle laminating line. |  | June - August 2004 |
 |  |  |  |  |  |  |  |
 |
| M. Kaindl Holzindustrie |  | Salzburg (Austria) |  | Mechanical and electrical installation of a Wemhöner short cycle laminating line as well as maintenance work and servicing of the ventilation plants, chip preparation and pressing plants in Wals/Salzburg. |  | March - July 2004 |
|
|
We are the leading provider of industrial plant installations for the wood based panels industry. In this sector, we offer worldwide mechanical and electrical installation of complete MDF, OSB and chipboard plants - and can even relocate your complete plant. Our range of services also covers installations in the following areas: woodyard, debarking, chippers, refining, sifters, dryers, gluing systems, forming lines and prepresses, cooling and stacking systems, sanding and sawing lines, packaging systems, short cycle laminating lines including environmental protection equipment, such as extraction plants filters, scrubbers and energy plants supplying thermal energy.
|