![]() Mechanical installtion of a clinker-production-line in Kolomna (RU) Mechanical installation of a clinker production line as well as 6.500 to. conveying systems including the silo feed and discharge, coal-crushing mill and diverse de-dusting units with a total capacity of approx. 16.000 to. Delivery of 191 to piping, duct and chute components Installation of approx. 25.000 m² Insulation ![]()
Cyclone- and dust removal systems Üxheim (Germany) Delivery and installation of steel construction as well as cyclone- and dust removal systems. Mechanical installation of machines, equipment and coating of the filter units. ![]()
|
|
||||