Grenzebach BSH GmbH

Complete mechanical and electrical installation of a gypsum plaster board production at BPB (Saint Gobain) in Matra, Hungary.

/sgscms/images/casestudies/P4010138.jpg

The project consisted of the mechanical and electrical installation of a gypsum plaster board production. Main component of the production was the 65 meter long dryer, the plaster board preparation station as well as the setting and take off line. Along with this, SGS was trusted with the planning, calculation, delivery and installation of the support construction for the heat exchanger. ...

more...

Heinzel Pulp Zellstoff Pöls AG

Mechanical installation of a rotary furnace and white liquor filter for Heinzel Pulp Zellstoff Pöls AG in Poels, Austria

/sgscms/images/casestudies/Bider für Film 015 Drehrohrofen Pöls.jpg

The project consisted of the complete mechanical installation of a production line for 440 tons per day of burnt lime and 5,700 m³/day of white liquor production. Kremsmüller was responsible for the complete installation of piping and container construction. SGS assumed the responsibility of the machine installation. ...

more...

Glaswool Musaffa ICAD IAbu Dhabi (UAE)Mechanical and electrical installation including plant component supply and piping.June 2009 – March 2010
Amana PlasterboardAbu Dhabi (UAE)Mechanical and electrical installations of a plasterboard plant incl. the calcination.October 2008 - June 2009
HolcimKolomna (Russia) Mechanical installation of a clinker-production line with a total capacitiy of ca. 15.000to.March 2009 – June 2010
SandvikGällivare (Sweden) Mechanical Installation of 2 crashing plants at the copper-mine Aitek-Boliden.March – December 2009
Ibau, LafargeMartres (France)Demounting and installation of a silo-plant with truck charging station, the pneumatic conveying systems and the planning and delivery of 60 to steel construction.since August 2008
HCCDubai (United-Arab-Emirates)Mechanical installation of a 115 to/hour cement mill with cement silos and packaging plant for the company CEMTEC in Sharjah. February - August 2008
ATEC GmbHMannersdorf (Austria)Demounting and mechanical installation of the thermal insulation of the steel construction, cyclone and pipelines for Lafarge Perlmoser.March - May 2008
GrenzebachHungaryMechanical and electrical installation of a plasterboard production line. Mechanical installation of a drying line, a preparation line and a setting- and take off line for the company BPB Matra.October 2007 - May 2008
Südbayerisches Portland ZementwerkRohrdorf (Germany)Winter revision and maintenance.since January 2007
Ibau, Kirchdorfer ZementKirchdorf (Austria)Mechanical installation of the equipment for the new cement-silo.April - September 2007
Ibau, Südbayerische PortlandzementwerkeRohrdorf (Germany)Mechanical installation of the pneumatic equipment for the filter dust conveying system.February - May 2007
PM-TechnologiesAltkirch (France)Dismantling and installation of cyclones, pipelines, conveyor elements, oven riser duct and powder pipes for the company Holcim.January - March 2007
Rigips (BPB)Bad Aussee (Austria)Mechanical Demounting and installation of pipelines. Installation of a 4 inch blast piping and main-supply unit of a  compressor, performance increase and rebuilding of the dedusting plant.December 2006
RigipsPuchberg (Austria)Demounting and installation of a gypsum-kettle including the ventilation-system.October - November 2006
ZPA Pöls AGPöls (Austria)Mechanical installation of a new rotary kiln and white liquor filter at the company Pöls AG.January - August 2006
Rigips (BPB)Puchberg (Austria)Mechanical installation of a Pfeiffer mill incl. ventilation systems, mechanical conveyor systems, crusher and sifting.January - February 2006
Loesche GmbHSteeg (Austria)Dismantling and Mechanical installation of a grinding mill at SGL Carbon Group.September 2005
Stone-Earth-Cement
In the stone-earth-cement industry, our main customers consist of companies in the cement, gypsum, building material and lime production sectors. We offer these customers services such as the mechanical and electrical installation of rotary kilns, heat exchange towers, drying, sifting and grinding units, plasterboard production lines, calcination, crushing and screening systems, material transport systems and environmental protection equipment. We also carry out renovation and restructuring, provide support in plant commissioning and also, on request, provide plant and equipment maintenance services. Depending on requirements, we can install whole plants or plant sections and can even procure low-tech components, such as steel structures, pipelines and insulation systems.

JOBS with SGS
We are looking for executives and specialist employees for projects abroad
© 2008 SGS INDUSTRIAL SERVICES GmbH Gewerbepark 1 | 4751 Dorf an der Pram | Austria | T + 43 (0) 7764 20 048-0 | F + 43 (0) 7764 20 048-14 | office@sgs-industrial.comIMPRINT  | DISCLAIMER | TERMS