SGS installed the electrical systems for a gas and steam power plant in Berlin Marzahn
Project data
- Commissioner
- Siemens Gas and Power GmbH & Co. KG
- Customer
- Vattenfall Wärme AG
- Industry
- Energy
- Construction location
- Berlin Marzahn, Germany
- Contruction period
- 12 Months
- Contributors
- 90
Scope of delivery & service
Electrical installation of a 270 megawatt electric and 230 megawatt thermal combined cycle power plant (CCHPP).
Electrical installation:
- Cable tray construction
- Cable pulling
- Measurement and control technology
- Cable connection
- Bus duct (generator branch)
- Transformer installation including oil filling
Our project scope
At the Berlin construction site, we took care of the classic tasks of cable tray construction, cable pulling, measurement and control technology, cable connection, bus duct (generator discharge) and transformer installation, including oil filling. For our employees, however, the project was somewhat unusual: the power plant is located in the middle of the city. This meant that there were no parking spaces and the workers had to use public transport to get to the construction site.