  SGS Industrial Services: Installation of the Isar HVDC converter station as part of the SuedOstLink project

Industry
Energy
Status
In progress
Country
Isar, Germany DE
Services
Construction management & supervision, Electrical installation, Project management
Building on the successful installation of the HVDC converter station in Wolmirstedt, SGS Industrial Services is applying its expertise to another key project: the electrical installation of the Isar HVDC converter station. Siemens Energy has once again placed its trust in the competence and reliability of our SGS team, placing a follow-up order that impressively underscores our performance and successful cooperation. The installation of an HVDC system is one of the most challenging projects in the field of energy infrastructure. SGS Industrial Services is meeting this challenge head on with cutting-edge technology, high precision, and a well-coordinated team.
95
Employees in action
 
16
Months of construction
 
7
large transformers
 
200
km Cable
 

Our Scope of Services in Isar

In the SuedOstLink project, we are responsible for the complete electrical installation of the Isar HVDC converter station, including the seven large transformers, each weighing 471 tonnes, and an extensive substation. 

Our services at a glance:

  • Installation of converters and cooling systems, including HV-Equipment
  • Installation of seven transformers including oil filling
  • Laying of approximately 200 km of cables, grounding rails and ropes
  • Assembly and connection of C&P cabins and systems
  • Installation of auxiliary systems and steel support structures
  • Implementation of lightning protection and parts of the grounding system
  • Installation of network and control cables
  • Carrying out bus and connection work to smooth commissioning

Over a period of more than 16 months, around 95 of our specialists are working to implement the system with the utmost precision, safety, and adherence to deadlines.

SuedOstLink: A Key Project for the Energy Transition

The Isar HVDC converter station is part of the SuedOstLink project – a 540-kilometer-long power connection stretching from Wolmirstedt near Magdeburg to Isar near Landshut. It transports renewable energy from the windy north to southern Germany, where electricity demand is particularly high.

To ensure that this energy can be transported over long distances with minimal loss, it is converted into direct current at the converter stations. At the end of the line, the electricity is converted back into alternating current and fed into the existing grid. This conversion enables safe and efficient transmission over hundreds of kilometers via underground cables.

SuedOstLink is creating one of Germany's most important electricity highways. The project ensures that renewable energy reliably reaches where it is needed. 

Through our work on SuedOstLink, we are making a direct contribution to ensuring the long-term viability of Germany's electricity supply in a sustainable and reliable way, working closely with our customer.

About Our Customer: Siemens Energy

Siemens Energy is one of the world's leading companies in energy technology and renewable energy. Its product portfolio covers the entire energy value chain, from generation and transmission to storage.

Safe. Global. Fast.

Worldwide projects on time & professionally.

YouTube is deactivated

We need your consent to use YouTube videos. For more information, see our Privacy Policy.

Vimeo is deactivated

We need your consent to use Vimeo videos. For more information, see our Privacy Policy.

Google Maps is deactivated

We need your consent to use Google Maps. For more information, see our Privacy Policy.