Major order: thyssenkrupp Polysius commissioned SGS with the mechanical and electrical installation of a complete cement clinker production line
Project data
- Commissioner
- thyssenkrupp Polysius France S.A.S.
- Customer
- Heidelberg Materials France Ciments
- Industry
- Stone/Earth/Cement
- Construction location
- Airvault, France
- Contruction period
- 3 years
- Contributors
- 500 at peak times
Scope of delivery & service
Mechanical and electrical installation, including piping installation, of a complete cement clinker production line with a capacity of 4,000 tons per day.
Mechanical assembly:
- 7,000 tons of steel construction
- 8,000 tons of mechanical equipment
- 350 tons of piping
- Double-shaft hammer crusher with a throughput of 1,200 t/h
- Longitudinal mixing bed
- quadropol® QMR² 45/23 roller mill with a throughput of 370 t/h
- Tangential mixing silo with a storage capacity of 10,000 t
- Single-strand, 5-stage dopol® cyclone preheater with integrated calciner
- 3-support rotary kiln
- polytrack® clinker cooler
- Processing plant for solid substitute fuels
- Dust extraction systems
Electrical installation:
- 800 km of cable installation
- 15,000 cable connections
- 28 km of cable support systems
Project overview
Our contract comprises approx. 7,000 tons of steel structures, approx. 8,000 tons of equipment, 500 tons of piping, and 800 km of cable.
Main components for raw material processing:
- Double shaft hammer crusher with a throughput of 1,200 t/h
- One longitudinal mixing bed
- One quadropol® QMR² 45/23 roller mill with a throughput of 370 t/h
- One tangential mixing silo with a storage capacity of 10,000 t for raw meal
Kiln line consisting of:
- dopol® cyclone preheater with integrated calciner
- 3-support rotary kiln
- Polytrack® clinker cooler
The plant also includes:
- A processing plant for solid recovered fuels (SRF)
- Dust extraction systems
Challenges & special features
The cement plant will remain in full operation throughout the entire construction period and commissioning of the new kiln line. In addition, the size and complexity of the project require good coordination and specific expertise in plant construction. Heights of up to 120 m and heavy lifts pose a challenge for our experienced SGS team.
New assembly method worldwide
The 120 m high dopol® preheater tower is being assembled for the first time using a new “upside down” concept (polfast®). Here, the preheater stages, including refractory lining and electrical systems, are prefabricated in parallel on a ground-level assembly platform. These individual segments are lifted and positioned from the inside. This process requires precise and safe work combined with good coordination.
State-of-the-art technology
The cement plant sets new standards in terms of safety and sustainability. The plant guarantees future-proof cement production with significantly reduced emissions.
About our customer thyssenkrupp Polysius GmbH
thyssenkrupp Polysius provides technologies, services, and modernization solutions for cement plants, focusing on optimizing performance and sustainability across the entire plant lifecycle. Leveraging deep process expertise, long-standing industry experience, and technology-driven optimization approaches, Polysius supports plant operators worldwide in improving operational efficiency and sustainably reducing emissions in existing assets.